FDOT Statewide Projects & Training

Print Project Status Summary

Project Type: Project
Project Name: Air Service Study - Completed 4/2012
Aviation Office Project Manager: Abdul Hatim
Consulting Firms (Prime and Sub-consultant, if applicable) : Kimley-Horn

Start DateFriday, July 29, 2011 Completion Date:  Monday, April 30, 2012
Project Description
The report entitled,"Analysis of Scheduled Commercial Air Service in Florida: Update 2008" completed in August 2009, will be updated to reflect the most current data regarding air service. The new update will now include a section devoted to air service profiles of Florida's commercial airports. The final deliverable will include a tri-fold brochure for air service in Florida. The project is scheduled to be completed in the April with a final PowerPoint presentation to the CFASPP statewide steering committee in Orlando.
Current Status (as of Monday, February 13, 2012)
The contract was executed on September 27th, 2011. The first task for this is to identify existing levels of domestic scheduled commercial airline service for each of the Florida markets (Summer 2011). Current service offerings will be identified for each non-stop city pair. Weekly flight frequency, aircraft equipment type used, carrier, and weekly seats for each non-stop route will be identified.